Macnamara Neighbourhood 02 – Offsite Works
Status: DA Approved - Detailed design underway
Responsible Entity: Ginninderry JV
Project Timeline
2020
Consultation on Macnamara Estate Development Plan 1 and Masterplan
Ongoing
Macnamara Estate Development Plan 1 Detailed Design and Construction
Q2 2023
Macnamara Estate Development Plan 2 Documentation Preparation
26 July - 9 August
Consultation on Offsite Works Development Application
Q3 2023
Anticipated Offsite Works Development Application Submission
1 December 2023
DA Submitted
2024
Anticipated DA Approval
Notice of Decision granted November 2024
Q2 2025
Anticipated Detailed Design Approval
Mid-2026
Construction Completed
Project Updates
1 December 2023DA Submitted
Project Background
Ginninderry have submitted the second Estate Development Plan (i.e., subdivision) Development Application (EDPDA) for Macnamara Neighbourhood 02, with lodgment in late 2023. To read more about this Development Application, please click here.
To enable future development in the area, an associated Development Application referred to as ‘Offsite Works’ is being delivered as a part of the consultation process for the second Estate Development Plan in Macnamara.
Offsite Works
The Offsite works will address the road connection (and associated works) between Pro Hart Avenue and Parkwood Road.
The offsite works will include the construction of a connection road between Pro Hart Avenue to Parkwood Road. This road connection will include associated landscaping, a pedestrian path, and a cycle path. Included in this works package is a shared path connection from Pro Hart Avenue to the suburb of MacGregor to enable a better connection into West Belconnen.
A water main is included in this works package to service the Ginninderry Development, this water main will be built along the proposed road alignment and continue along Parkwood Road to O’Reilly Street MacGregor.