Ginninderry Tool Library

Status: Tool Library Launch
Responsible Entity: Ginninderry JV & Heather

Project Timeline

March 2023

Community Grant application recieved

Heather submitted a successful community grant application as part of the 2023/2024 community grant funding.

H2 2023

Initial investigation

Work was carried out to explore opportunities for a temporary location

June - October 2024

Consultation with Tool Library Manager

To determine location and arrangement of Tool Library.

November 2024

Tool Library Shipping Container

Installed at the Ginninderry Temporary Dog Park

December 2024 - March 2025

Establish of Tool Library

Including software platform, procedures and purchasing of tools.

TBC

Tool Library Launch

Project Updates

26 November 2024Tool Library delivered on site