Bonthrone Street Temporary Median Crossing Closure

Status: Notification
Responsible Entity: Ginninderry Joint Venture

Project Timeline

2018

EDP approval for Strathnairn Stage 1

Estate Development Plan Approval was granted for Strathnairn Stage 1.

Refer to the Q&A section below for a copy of these Plans.

September 2019

Temporary Traffic Management Plan approved for GX Display Village

Temporary Traffic Management Plan (TTMP) was approved for the GX Display Village. Signage was installed at Pro Hart Avenue / Lionel Rose Street intersection notifying access to Bronthrone Street was for display village traffic only. Road blocks placed at Bonthrone Street, Yeomans Street & Gullifer Street to allow for pedestrian only access to the display village. Temporary car park constructed on Bonthrone Street for the GX Display Village.

October 2019

GX Display Village Opens

GX Display Village opened in October 2019 with temporary median crossing access provided to allow for access to the display village carpark. Yeoman Street open for pedestrian access only.

January 2023

Community Workshop - Discussion of closure of display village and associated works

At the 'Roads, Traffic and Parking' community workshop in January 2023, an update was provided about the closure of the display village, including the closure of the temporary median. In February 2023, an EDM was sent out to all residents in our database with a copy of the Listening Report from the community workshop.

Refer to the Q&A section below for a copy of the Listening Report.

End of April 2023

GX Display Village Closed

Main GX Display Village closed.

1 May 2023

TTMP modified to reflect closure of main GX Display Village

TTMP modified to allow main GX Display Village to close. Yeoman Street opened for vehicle access. Road block on Bonthrone Street & temporary median crossing remain to allow for McDonald Homes to continue operating two display homes on Bonthrone Street. Approval was given by ACT Government for this TTMP until 1 May 2024.

16 April 2024

Notification of removal of TTMP works

Letters were distributed to immediate residents as well as cars parked on Pro Hart Avenue near Bonthrone Street during letter distribution. Letters are also available at The Link. Strathnairn Arts Association members and visitors were also provided with a letter of notice noting new exit arrangements along Yoornie Way.

17 April 2024

Signs erected on Pro Hart Avenue

Additional signage was placed along Pro Hart Avenue and at the temporary median crossing to notify all residents of the upcoming works. Exit signs placed on Gullifer Street for visitors exiting Strathnairn Arts Association.

29 April 2024

Work begins to remove temporary median crossing

Construction works to remove the temporary median crossing to commence.

1 May 2024

TTMP Expires

TTMP expires on 1 May 2024. All traffic arrangements will return to those as approved in the development application and works as executed plans of 25 February 2019.

  • Row Image

Background

A Temporary Traffic Management Plan (TTMP) was granted in 2019 to accommodate the GX Display Village in Strathnairn. This TTMP involved placing a temporary median crossing through Pro Hart Avenue to allow access to Bonthrone Street, the placement of jersey kerbs (temporary road blocks) on Bonthrone Street as well as directional signage.

This TTMP expires on 1 May 2024, and work to return Pro Hart Avenue to its original design will commence on 29 April. Affected residents are encouraged to familiarise themselves with the available alternate route—an example via Yeomans Street is illustrated in the accompanying image.

Q&A

A Temporary Traffic Management Plan (TTMP) was granted in 2019 to accommodate the GX Display Village in Strathnairn. This TTMP involved placing a temporary median crossing through Pro Hart Avenue to allow access to Bonthrone Street, the placement of jersey kerbs (temporary road blocks) on Bonthrone Street as well as directional signage.

The TTMP can be found via the following link: https://ginninderry.com/wp-content/uploads/2024/04/Display-Village-TTMP-from-01052023-to-0105202477.pdf

After further consultation with our traffic engineers, they have advised us that the permanent retention of the crossing would not comply with ACT Government road standards. While it was acceptable as a temporary measure when the Bonthrone/Yeoman Street intersection was closed, the Pro Hart Avenue crossing would not meet safety or performance requirements as a more permanent arrangement.

Signage denoting the crossing as temporary was installed in accordance with the government-approved Temporary Traffic Management Plans (TTMP) that has been in place since 1 September 2019. Additionally, Ginninderry highlighted the future closure of the intersection at the Roads, Traffic & Parking Community Workshop in January 2023. The Listening Report from this workshop was shared with our Purchaser and Resident email database in February 2023. Finally, Ginninderry issued a letter to immediately affected community members on 16 April 2024.